WSJF
Cost of delay ÷ job size
- Best for
- sequencing agile flow
- Time
- 30–60 min
- Difficulty
- Intermediate
Example
Sequencing a SAFe agile backlog by weighted shortest job first
WSJF priorities
- Compliance audit fix — Cost of delay 21 / job size 3 = 7.0
- Top-customer SSO request — CoD 18 / size 5 = 3.6
- API rate-limit overhaul — CoD 15 / size 8 = 1.9
- Reporting redesign — CoD 12 / size 13 = 0.9